A third fire hall will be built on the east side of the City of Leduc. Construction is expected to take two years to complete. The location of the new fire hall will enhance emergency response capabilities in the industrial area and provide improved coverage for residential areas.

Fire Hall 3 will be single-story building and include:

  • Six dormitories
  • Offices
  • Dayroom
  • Workout room
  • Classroom
  • An apparatus bay with two double-length bays
  • Gear storage
  • Maintenance rooms
  • A mezzanine
Map of Leduc showing locations of Fire Halls 1, 2, and 3, marked with icons. Major roads and Telford Lake are visible.
Project Update

Construction Project - Firehall 3

Date Status
April 30 Topsoil stripping is complete. Clay fill import for under the building is ongoing. Site servicing work is scheduled to start next week.
May 15 Site servicing to building is complete. Clay import to building pad is complete. Under-building services will start this week, with pile installation to follow in the coming weeks.
May 29 Under building service installations are complete. Pile installation has started and will continue next week. Grade beam excavation and formwork will follow.
June 13 Pile installation is completed. Grade beam excavation has commenced and gradebeam formwork and placement will continue next week.
June 26 Gradebeam excavation is completed. Gradebeam and pilecap formwork is ongoing and will continue next week. Gradebeam concrete will commence next week.
July 24 Gradebeam and pilecaps are complete and backfilled. The sanitary line within the building has been installed. Underslab service installation will continue. Erection of the precast panels for the apparatus bay will commence next week. Earthworks for the 65th Avenue drivelane connection have started.
August 7 Under building deep services with risers are complete. Precast panels have been erected; welding of the panels will continue through next week. Rough grade of the driveway connection to 65 Avenue is completed. The office area subgrade compaction is completed; slab preparation will commence at the end of next week. Underslab and site electrical work will commence next week. Structural steel erection will commence in the next two weeks.

Construction Information

Contact: (780)-980-7107 / [email protected]

Construction Timeline: Spring 2025 – Fall 2026

Funding: City of Leduc

Have a question about this project? Please fill out our online contact form.