65 Avenue
The QEII and 65th Avenue Interchange project is a joint effort between the City of Leduc, Alberta Transportation, and the Edmonton Regional Airports Authority. It will support tremendous growth and development in the City of Leduc, Edmonton Metro Region, as well as provincially and nationally.
Construction is expected to take approximately 2-3 years, open in 2025. The work is anticipated to include some temporary closures of the existing flyover, but all efforts will be made to mitigate traffic impacts to the QEII.
The project is estimated to cost $112 million and is being funded through a cost-shared agreement between the Government of Alberta ($96.4 million) and City of Leduc ($15.7 million).
This critical infrastructure will support safety and ease of movement of people and goods. It will stimulate Alberta’s continued economic development through investment growth, job creation, and diversification. It will foster increased trade and improve transportation logistics in support of access to and from the Edmonton International Airport (EIA) and investment on airport lands and throughout the Edmonton Metropolitan Region.
Construction updates
Detours and closures
April 28, 2023 to summer: closure of on-ramp heading north on 50 Street to the QEII. We do not anticipate having to close it again (if all goes according to the plan) for the remainder of the 65 Avenue and QEII Interchange project.
On/off-ramp realignment: permanent closure of on-ramp west of Leduc Towne Square
Date | Status |
May 29, 2023 | 50 St. & 65 Ave roadwork continues with asphalt removals complete on the on ramp. Stripping for new ramp alignment and signals to be removed at the intersection starting this week. Airport fencing and gravel for the security road will be starting this week. Stripping of the perimeter road has started. |
May 23, 2023 | Wall construction has been delayed due to a delay in receiving materials. Completion of the wall is still anticipated to be completed by the end of the year. Noise barrier wall traffic accomodation setup, access construction/continue removal of existing chain link fence, and installion of a temporary security fence will continue in June. |
May 12, 2023 |
To help alleviate congestion by the 50 Street and 65 Avenue area due to the on-ramp closure, we are changing Sparrow Drive to local traffic only and asking motorists to detour from 65 Avenue onto 45 Street to Airport Road onto the QEII. Alternatively, to bypass the highway and get into Edmonton, take Range Road 250 (Nisku Spine Road). |
May 11, 2023 | 50 Street roadwork continues with Fortis relocating power lines followed by hydrovacing. Noise barrier wall work continues with the its removal. |
May 4, 2023 | 50 Street roadwork continues with on-ramp onto QEII remaining closed and Fortis is relocating power lines. Noise barrier wall work has started with the removal of the guardrail. Hydrovacing of utilities and removals of existing fence will start next week. |
May 1, 2023 | Fortis will begin relocating power lines the first week of May and concrete removals continue. |
April 25, 2023 | On April 28, the on-ramp to the QEII from 50 Street (northbound) will be closed till late summer. Motorists will need to detour onto Sparrow Drive to take the next on-ramp off Airport Road to the highway. The outer right lane on 65 Ave between Sparrow Drive and 50 Street will also be closed. The outside lane on 50 Street southbound from the off-ramp to South Highway Avenue will be closed for widening work. |
April 20, 2023 | Median and curb removal continues on 50 Street. On ramp west of Leduc Town Square closed and electrical relocates start next week. |
April 14, 2023 | One lane in both directions along 50 Street between 64 Avenue and 65 Avenue will be closed to start median and curb removal. Realignment of the on/off ramp west of Leduc Towne Square will begin with the closure of the on-ramp to the QEII. |
In 2023, 65 Avenue and QEII Interchange construction will include:
- Reconstruction of 50 Street and 65 Avenue on the east side of the QEII
- The build and re-alignment of the fencing along the Airport Perimeter Road
- An extended road along Airport Perimeter road to connect with 65 Ave on the westside of the QEII
- Prepare the ground for the build of foundational piles for the overpass bridge
- Construction of a noise barrier wall along the Willow Park neighbourhood
- General ground work preparation for the two roundabouts, the overpass, and detour roads along the QEII highway
- Realignment and closure of the on/off ramp road along Leduc Towne Square
- On-ramp will be closed permanently.
- Off-ramp will be re-aligned and remove access from 60th Avenue utility road.
We ask motorist to abide by the posted signage in the construction zones that reflect the traffic pattern changes. We appreciate your cooperation and patience.
What will be built
- A new overpass over the QEII
- New on-off ramps from the QEII
- Improvements to some existing ramps
- Intersection improvements at 65 Avenue and 50 Street in Leduc
- Completion of Perimeter Road and 65 Avenue, west of the QEII
- Improvements to Grant MacEwan Boulevard
- A pedestrian crossing over the QEII via a multi-use trail
- A sound barrier wall south of 65 Avenue on the east side of QEII (impacted residents will be contacted directly; more details to come)
- Learn more about the project planning and design and view an overview map of the project
Project milestones
- Nov. 30, 2022: Province and City break ground of 65th Avenue Interchange project
- May 13, 2022: Fully funded: new interchange drives investment, creates jobs
- Jan. 25, 2019: New interchange to create jobs, attract investment
- June 9, 2017: Design for new Leduc interchange jointly funded
Questions
Contact us at 780-980-7107 or engineering@leduc.ca