The following roads will undergo surface overlays this season to ensure their continued stability and safety for years to come.

  • 50 Street (54 Avenue to 51 Avenue)
  • Coady Boulevard (Rollyview Road to 33 Avenue)
  • Corinthia Drive (50 Street to Bella Coola Drive)

Surface overlay roadwork involves removing the aging asphalt surface and replacing it with new surface to improve road structure and mitigate the requirement for more extensive reconstruction.

There may be temporary periods of lane closures and detours for motorists. Please follow signage in the area and drive the posted speed limit.

Map shows 50 Street construction project in 2025, highlighting the overlay program area between 50 Avenue and 55 Avenue.

50 Street Road Overlay Construction Map

Map showing 2025 construction projects on Caledonia Dr and Cosby Blvd with surrounding streets and a small lake.

Coady Boulvevard Road Overlay Construction Map

Map showing a road construction overlay project at Nootka Rd from 50 Street to inside the Corinthia Park area in 2025.

Corinthia Drive Road Overlay Construction Map

Project Update

Construction Project - Road overlays

Date Status
Corinthia Drive Overlay
July 3 Construction is planning to begin July 7 and will include concrete replacements for select portions of the sidewalk on the north and south sides of the road, followed up with milling of existing roadway and new asphalt paving. There will be no parking on Corinthia Drive during construction in order to maintain one lane of traffic in each direction, while also closing a lane for concrete replacements to take place.
July 17 Corinthia Drive Overlay: Sidewalk removals have occurred on the north side of the road, base work has started and gravel is being placed for the new sidewalk.
July 23 Crews continue to work on the north side of the road. Due to recent rain the excavations will need to be dried out and recompacted.
July 30 Crews continue to dry out the north side of the road for concrete placement.
Aug. 14 The sidewalks on the north side of the road have been completed, sidewalk removal has begun on the south side of the road.
Coady Blvd Overlay
Aug. 14 Carmacks will begin milling of Coady Blvd on Saturday, August 16, with plans to pave the road on August 19-20.

Construction Information

Contact: (780)-980-7107 / [email protected]