Willow Park will see continued neighbourhood renewal work with road and sidewalk reconstruction on 51 Avenue, 52 Avenue, 54 Avenue, 51 Street and 51A Street to ensure continued stability and safety for years to come.

In addition, water main work will be done on 51 Avenue and stormwater infrastructure upgrades on 54 Avenue and 51 Street to improve drainage in the area as identified by the Stormwater Master Plan.

There will be temporary impacts to street parking, access to driveways, mail delivery, and bussing to complete the work as efficiently as possible. Residents in the area are encouraged to watch for signage and additional details from the contractor throughout the season. Notices will be delivered to houses prior to closures to give advance warning of construction impacts.

Note: If you have new concrete installed on your property, the application of ice melt can cause damage. The City recommends using sand to control ice on new concrete for the first year. Free sand and chips bins are placed around the City for you – find your closest bin location.

Map showing construction projects in 2025 with highlighted roads for reconstruction and utilities near Willow Park School.
Project Update

Construction Project - Willow Park

Date Status
May 7 Hydrovac and exploratory work is expected to begin the week of May 12. Road closures on 54 Avenue near 50 Street are anticipated to begin on May 20 for underground installation. Air spading for tree root evaluations is expected to begin later this week or next week.
May 14 Initial exploratory hydrovac of utilities is taking place this week on 54 Ave at 50 St. 54 Ave from 50 St to 51 St is expected to be fully closed beginning May 20 as underground work begins. Work on 51 Ave from 50 St to 51 St is expected to begin late next week. Resident notices are being distributed this week to those directly affected by road closures next week.
May 22 54 Avenue is now closed from 50 Street to 51 Street for removals and beginning of the storm main installation. Temporary water is being set up on 51 Avenue from 50 Street to 51 Street in preparation for the water main replacement that will soon begin in this area. The temporary water allows residents and businesses to continue to receive city water as usual while the main distribution line is replaced.
May 29 Preparations continue on 54 Avenue for storm main installation. 51 Avenue is now on temporary water and work has begun on the water system. Road construction is expected to begin on the Willow Park Estates West Access and the bulb on 51A Street next week.
June 5 Replacement of the water distribution system on 51 Avenue and 51 Street has started with work on hydrants, valves and beginning on the main line. Utility conflicts continue to cause challenges on storm main installation on 54 Avenue. Road work is has begun on the west access to Willow Park Estates and is expected to begin soon in the bulb on 51A Street.
June 13 Subgrade prep work and cement stabilization is taking place at Willow Park Estates west access and the bulb on 51A Street. Gravel will follow, then concrete will begin once ready. Work continues on the water main replacement on 51 Avenue, with crews having to respond to an emergency water main break at 52 Avenue and 51 Street mid-week. A new hydrant has been installed, and several valves have been replaced as part of this project in order to isolate the water system throughout construction.
June 19 Concrete curbs and gutters are being poured in the 51A Street bulb and west Willow Park Estates entrance this week. Gravel will follow once concrete is complete. Work continues on watermain replacement on 51 Avenue.
June 26 Concrete work and gravel continue in the 51A Street bulb and west Willow Park Estates entrance this week. 51 Avenue watermain replacement continues. Rain caused delays but work is continuing.

Construction Information

Contact: (780)-980-7107 / [email protected]

Construction Timeline: Spring – Fall 2025

Funding: City of Leduc

Have a question about this project? Please fill out our online contact form.