Willow Park Inclusive Playground
A new inclusive playground will be constructed south of Willow Park School, designed with input collected from the community in January 2024. The playground upgrade will also assist with improving drainage challenges adjacent to the school.
Contact: | 780-980-7107 / engineering@leduc.ca |
Timeline: | Summer - Fall 2024 |
Funding: | CFEP grant, Canadian Tire Jumpstart Capital Program, City of Leduc, Kinsmen Club of Leduc |
Playground design
Project Update
Date | Status |
Sept. 12 | Most of the playground equipment arrived on site this week and will be assembled over the next couple weeks. The barrier curb was poured and holes are being dug for the equipment posts. The gravel base and rubber surfacing will follow the equipment. |
Sept. 4 | The drainage system is expected to be installed along with gravel work this week. Form building to following with pouring the concrete barrier curb and pad. Equipment installation anticiapted to begin next week. |
Aug. 28 | The underground drainage system will be installed in the coming weeks, along with the gravel pad and concrete barrier curb. Playground equipment bases are expected to begin installation within the next two weeks. |
Aug. 15 | Demolition and base prep for the new playground was completed this week. Construction of the new playground will commence in September. |
Aug. 1 | Demolition of the existing playground is complete and earthworks is expected to begin in the next couple weeks. |
July 18 | Demolition of the existing playground and earthworks are expected to begin in the next week. The existing playground on the south side of the school will be unavailable, however the other playgrounds at the school will remain open. |
Feedback
Have a question about this project? Please fill out our online contact form.