Storage Yard Environmental Assessment

(located at 3719 48 Ave)

Funding Support: Green Municipal Fund
Timeline: 2021
Questions about this project? Project Manager:  Shelby Lowe
Email:  engineering@leduc.ca
Phone:  780-980-7107

Overview:

  • A Phase I Environmental Site Assessment (ESA) conducted at the City’s Public Works Storage Yard in Lede Park identified several areas of potential contamination, such as street sweepings, soil piles, and a hydrovac pit.
  • A Phase II ESA then identified the need for a Supplemental Phase II ESA and groundwater monitoring in 2021.
  • Following the Supplemental Phase II ESA, we will determine if a Remedial Action Plan and further work is required by Alberta Environment and Parks.

Project Updates

DATE STATUS DETAILS
Sept. 3, 2021 On-time Soil sampling and groundwater monitoring is planned for fall 2021.
2021-04-12 On-time The request for proposals has closed, and consultant selection is underway for the Supplemental Phase II and Groundwater Monitoring.